密查电影在线观看完整版|行尸走肉第7季在线观看免费完整版|欧美区日韩区|五月婷婷深爱五月,一级不卡免费视频 ,色戎 同类电影大尺度未删减版,国产色宗合

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱(chēng) 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(6)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(6)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project manager in the control quality product inspection process discovers that a product currently manufactured has a design defect that could potentially reoccur in the company’s future projects. The project manager known the problem can be solved with a minimal Stander change. What should the project manager do next?
A、Continue with the project as planed and leave the improvement for another project.
B、Recommend a standers update.
C、Update the quality management plan.
D、Wait until the next project manager’s meeting to notify other project manager of the problem.


相關(guān)試題

推薦文章